So,
those factors aside – what’s so different about our
installation? We decided to stain the floor and use it as an
exposed system. Sure, now that I’ve said it, it seems
obvious. But you should have seen the looks on the design
teams faces when I announced that this is what we were going
to do.
Concrete
staining is not new. Normally on a raised floor you would
install carpet tile. As is inevitable with any carpet tile,
reconfiguration of the floor will require replacing
previously cut carpet tile with full pieces. In the big
scheme of things, this is not a large issue – it just
means you have to keep attic stock. We had a new idea – if
you eliminate the carpet tile, you eliminate the need for
attic stock. Less materials to maintain equal lest cost,
both initial and long term.
Let
me outline our design scenario. As with any renovation, we
were faced with multiple items that needed addressing. We
were converting space, previously been utilized as shop
space, into administrative office space. None of the
electrical was able to be reused; it was previously fed from
the ceiling and along the walls – walls that were to be
removed. As new office space we needed a suitable electrical
distribution system that could feed non-powered modular
furniture wall systems while also being able to accommodate
future reconfigurations. Dropping out of the ceiling into
power poles, while functional, was not the answer.
Further
complicating this was the construction of the slab. This
being a prior military facility, it was designed to last
forever. Our initial coring determined that the slab was a
minimum of 8 inches thick. On top of that, several of the
walls that were scheduled for removal sat upon bond beams,
with the adjacent slabs spanning in between. Removal of the
walls left us a wide open space with a large variation in
finished floor heights.
Economically,
it was infeasible to saw cut the slab and install a new
electrical distribution. Equally infeasible was floating out
the slab to correct the varied finish floor heights. Using a
raised floor system could correct both these issues.
I
had previously used this type of floor system on several
projects (click
here to read more about what makes up these systems, and
what they can do ). However, there was one more design
criteria that we needed to meet. For this type of facility,
it is highly probable that we will have higher than normal
levels of dirt in the facility. We specifically did not want
carpet in the administration areas, as it is significantly
more difficult to clean grease and tar out of carpet when
compared to concrete.
I
consulted Paul Kinsella with Allied Interiors, the
distributor that I had used several times in the past. We
explained what we wanted to do, and we were hoping that this
had been done before; after all, there is no need to
reinvent the wheel. We quickly found out that this was not
an entirely new concept. There are raised floor systems that
don’t use carpet – unfortunately, the vinyl tile
computer look was not the aesthetics we were trying to
achieve. They did offer a clear sealer that really brings
out the nature of the concrete. But this system was also
going to serve as a design element, and we needed color.
Because
of the way that the panels are manufactured and sorted, I
knew that there was no way to ensure consistency of stain.
So, this aspect was designed into the system. If we did all
the panels the same color, the color would be close but not
an exact match. When placed side by side, you would be able
to distinguish a change in color across the floor. Factoring
this into the equation led us to use several different
colors. My original intention was to install the panels in a
random mosaic pattern. While sounding good in theory, we
needed to keep the color selection to a minimum. My
contractor came up with the idea of installing the panels in
a diagonal pattern – this was definitely the correct
solution!
We
used our painters to stain the panels on site. The biggest
challenge with this was allowing for the low VOC content of
the stain, since this was a LEED building. The first stain
that we used was within the VOC limits, but had no other
favorable qualities. The panels looked so hideous we
didn’t even take them out of the truck. Once the painters
realized that I wasn’t going to give in, they gave a
concerted effort and found an appropriate stain. Once the
initial colors were approved, we had the panels delivered to
the site and spread out in one of the bays. Here you can see
the staining in process.
Installation
was pretty standard. As you can see, we decided to wait to
seal the floor until it was installed. This would cut down
on touch- ups, and ensure a consistent depth of sealer. The
panels soak up the stain like a sponge. It’s not until the
sealer is applied that the true color comes out.
We
did have to do one additional step before sealing the floor.
I had the contractor back out all the screws about a quarter
of an inch before the sealer was applied. This was so that
in the future when reconfiguring the space, we would not
have to worry about chipping when unscrewing the panels. The
very last step was fully removing the screws and replacing
them, due to the amount of sealer in the heads. We also
utilized a gasket system at the perimeter to account for an
air tight seal between the panels and the exterior wall.
What
other items do you need to take into consideration when
using an exposed stained raised floor system? It is best to
do a layout similar to a reflected ceiling plan. Minimize
your cuts, and establish a starting point for full panels.
In this case, we poured our stairs, ramps, and landing out
of concrete for a finished look.
We’ve
now covered the aesthetics of the system, and you’ve sold
the Architect and Owner on the idea. But what about your
Mechanical and Electrical Engineers? In a future article we
will discuss the components that we used for electrical and
mechanical distribution, along with the benefits and
limitations. Stay tuned!