|
Fly
Ash Concrete
by
Betsy del Monte
In
the name of sustainability, many construction practices and
attitudes are being reconsidered. What used to be thought of as
an unusable material is proving to have some real
advantages...and challenges. Here are some questions, and
answers about using fly ash in concrete.
Why
are concrete and the cement used to make it targets for
increasing sustainability?
-
Concrete
is second only to water as most consumed substance on earth,
and demand continues to increase dramatically.
-
Cement
manufacturing operations are responsible for almost 8% of
global emissions of carbon dioxide, a significant greenhouse
gas.
-
For
every ton of cement manufactured, about 6.5 million BTU’s of
energy are consumed -- about one ton of carbon dioxide is
released.
What
is High Fly Ash Concrete?
Fly
ash is defined in cement and concrete terminology as "the
finely divided residue resulting from the combustion of ground
or powdered coal, which is transported from the firebox through
the boiler by flue gases."
In other words, fly ash, a by-product of coal-fired
electric generating plants, is the dust left over after the coal
burns.
Fly
ash can be used in place of cement to create concrete for
construction. Two
classifications of fly ash are produced, according to the type
of coal used. Class C fly ash is produced by burning lignite or
sub-bituminous coal. Anthracite
and bituminous coal produces fly ash classified as Class
F.
How
can using Fly Ash in place of cement help?
Using
coal fly ash conserves energy by reducing the demand for typical
pavement materials such as lime, cement and crushed stone, which
take energy to produce. If all the fly-ash generated each year
were used in producing concrete, the reduction of carbon dioxide
released from cement production would be equivalent to
eliminating 25% of the world’s vehicles.
-
Every
ton of ash reused in cement products equates to nearly a ton
of CO2 savings.
-
Each
ton of fly ash used to replace a ton of cement saves the
equivalent of nearly one barrel of imported oil.
-
Every
ton of coal combustion product that is recycled is a ton not
deposited in our landfills.
How
Does Fly Ash Affect Concrete?
-
Fly
ash creates stronger concrete, but strength may develop more
slowly than all portland-cement concrete.
-
Fly
Ash is easier to place, pump, work and finish.
-
Fly
Ash can be mixed in proportions which make summer concrete
finishing easier, due to slower set.
-
Care
can be taken to mix proportions which don't affect winter
finishing.
-
Concrete
will require less water, resulting in less shrinkage and
cracking.
A
CASE STUDY
Where
has fly ash bee
n used locally?
The
RadioShack Corporate Headquarters, in Fort Worth, recently
received a LEED Silver certification.
This project was designed by HKS, and constructed by The
Beck Group, with Walter P. Moore as the structural engineer.
Concrete was provided by Latimore.
At
the end of the project, there was over 1,500,000 sq.ft. of
elevated slab formwork, 82,000 cu.yds. of concrete poured, and
almost 14,000 cu.yds./ month placed during peak periods.
First
steps to determining the feasibility of using fly ash concrete on
a project.
The
project team set a goal to develop and use concrete mixes with a
minimum of 51% fly ash content, in order to qualify for the two
LEED points dealing with recycled materials. First, the design
team researched case studies from other projects, received
feedback from industry experts, and involved local ready-mix
suppliers/installers. It quickly became apparent that fly ash
concrete was readily available from most concrete suppliers.
It
was also necessary to collect and evaluate performance data on
fly ash concrete. Testing was done first in the lab, with 65
different mix designs. The testing focused on the variables of
set time and strength gain. The lab results showed that:
-
Ultimate
design strength was as high if not much higher.
-
Early
strength target is achievable.
-
Use
of admixtures were a must for early strength and set.
-
The
mixes were less forgiving, and stressed the importance of the
Quality Control process.
-
Class
‘F’ fly ash preferred over class ‘C’, primarily for
color.
-
Slag
use not feasible due to cost/supply constraints.
Next,
testing went to the field where selected mix designs in truck
loads of 4 cubic yards, were poured, finished and tested by
casting multiple test panels, slabs and columns. Subcontractor
crews were asked to work different mix designs. All pours were
tested for workability, set time and strength development time.
The field tests showed that:
-
51%
fly ash mixes have a different “feel” and will require
different finishing techniques.
-
Additional
wait time to initial set, less working time available between
set and troweling.
-
Mixes
are pumpable; with higher pressures on equipment.
-
Greater
potential for surface cracking; requires wet curing and
evaporative retarder re-application.
-
More
difficulty in controlling slump.
-
Additional
Quality Control measures were required at plant and job site.
-
Minimal
to no cost increase for ready-mix material (savings in cement
offset by cost of admixtures).
Subcontractors
that participated in field testing were surveyed to get opinions
and recommendations on issues such as concrete placement and
workability, slab finishing techniques and crew productivity.
They were also asked to comment on any contributing factors
to cost increases. The survey resulted in the following comments:
-
Will
require different finishing techniques & bigger crews.
-
Working
time after initial set is reduced considerably.
-
Pour
sizes may have to be reduced to get quality slabs.
-
Surface
cracking concerns on hot or windy days; wet curing method will
probably be required. Evaporative retarder helped.
-
Doesn’t
hold a “broom” finish well (parking garage slabs).
-
Quality
control of material will be very critical.
Proposed
Solutions to these concerns:
-
Place/Finish
Crew Productivity Loss
-
Additional
Evaporative Retarder use
-
Wet
Curing of Slabs
-
On-site
QC Control & Material Testing
-
Concrete
heating for cold weather pours
Estimated
costs for above = >$500,000
Potential
Schedule Impact:
-
Strip
forms 3 days after slab pour vs. 2 days
-
Adds
3 weeks to schedule of each building
-
Smaller
slab pours, more mobilizations by place/finish crews
-
Slower
formwork cycling
-
Wet
curing slabs, extended formwork cycling time
Team
Conclusions
The
RadioShack team considered all these issues before deciding how to
proceed with the concrete. They realized that the cost impact for
51% fly ash throughout was greater than had been anticipated.
While some areas of the structure (piers and foundations)
would be less affected, because of the large project scale, there
were higher risks for cost, schedule and quality. The risk of
major schedule impact was a real possibility, but difficult to
measure. It was
realized that the quantity of fly ash needed for one LEED credit
point was attainable; but the additional point could be better
earned in some other ways.
The
FINAL decision
Fly
ash can be a very effective way to substitute for some of the
cement in any project’s concrete, but care must be taken when it
is used in higher percentages.
If the schedule has some flexibility, sufficient or
superior strengths can be obtained. All these factors should be
considered to be able to use the maximum amount of replacement fly
ash in each project.
At
RadioShack, the final decision was made to:
-
Utilize
HVFA concrete in selective areas of project, that will not
impact cost / schedule:
-
51%
fly ash mix used in all piers
-
30%
fly ash mix used in other foundations
-
20%
fly ash mixes used in slabs and columns
One
LEED credit point achieved for fly-ash use (not 2)
23%
average of total project concrete volume
For
more information on RadioShack, click here.
Betsy del Monte is an architect with 24 years
of experience, and the 2006 Chair of the USGBC North Texas
Chapter. She has worked on a multitude of projects ranging from
schools and churches to million-square-foot commercial buildings.
As a principal with Beck, she leads both integrated teams of
architects and contractors, and architecture-only projects.
For additional information
regarding this article, please contact Betsy at betsydelmonte@beckgroup.com.
All
comments are the sole responsibility of the author.
This
article was originally posted 6/27/06.
|