The
McKinney
Green
Building
Project Overview
HDR
is working with West World Management to incorporate
sustainable elements from all categories of the USGBC LEED
program into its
McKinney
Green
Building
. Since the
McKinney
Green
Building
is a speculative office building, HDR and the owner focused
on incorporating features that contribute to high energy
efficiency and excellent indoor environmental quality.
Concentrating on these items will help reduce
long-term operating costs and provide high-quality space for
future tenants. The
building, at
4500 West Eldorado Parkway
in
McKinney
,
Texas
, is located on a three-acre parcel of land adjacent to a
large multi-family apartment complex.
This
article explains the design team’s process during the
development of this exciting project, now under
construction.
Pre-Planning,
Space Programming
Proper
planning during the early phase of a project is critical to
success. The HDR
project team and the owner developed a space program and
project budget. During
this pre-planning phase, the team found that the owner was
interested in developing a significant sustainable project
equal to a LEED platinum building.
Some of the most significant items the owner focused
on were in the Energy and Atmosphere credit category.
With the goal of reducing energy consumption in the
building by over 60 percent and incorporating on-site energy
generation into the project, the team discussed the budget
needed to support these sustainable commitments.
LEED
Workshops
During
the pre-planning and space programming phase, the team also
held Sustainable Design Workshops.
For two days, we discussed sustainable design
features focusing on the five basic LEED categories.
We developed a list of ways to incorporate
sustainable design elements into the office building and
discussed the practicality of these items.
An
example was the concept of operable windows.
These can be an important element in getting fresh
air into an office building, thus improving indoor air
quality. However,
with building security issues, maintenance, and concerns
with HVAC system control, the team decided this was not an
option for this project.
Design
Phase
Early
on in the design phase, the team worked closely with a
day-lighting consultant to discuss building orientation,
fenestration, shading opportunities, building layout and
floor plate depth.
We also developed site options, including
different building orientations, parking layout options and
site access. The
owner wanted a minimum of about 60,000 square feet of office
space on the three-acre site, so efficient use of the site
for parking, landscaping and drainage were important.
Parking decks and underground parking were discussed.
In the end, the most efficient way to orient and
develop the site was with a simple rectangular floor plate
centered on the site with parking around the perimeter.
The
building floor plate was developed to accommodate an
open-office arrangement on the building’s three tenant
floors. The
shallow building depth, higher ceiling spaces and many
windows allow for more natural daylight.
The non-occupied spaces, including mechanical rooms,
electrical rooms, telephone and data rooms, elevators and
stairs, are located in the building core in the center of
the floor plate, which provides the most efficient use of
space and distribution of systems to different floors.
During
the design phase, the team investigated the efficiencies and
long-term savings of different HVAC systems using energy
modeling. The
modeling was based around ASHRAE standards.
The different HVAC systems modeled included “solar
hot water absorbers,” “geo-thermal heat pump” and high
efficiency standard systems.
The initial design for the building used the solar
hot water absorber system.
Due to complexity and cost of this system, it was
replaced with a geo-thermal heat pump system.
Additionally,
the team decided to use under-floor air distribution in the
project. The
lighting system selected for the tenant spaces will have
occupancy sensors and daylight sensors, enabling the lights
to shut down automatically when not needed.
The R-Value for insulation in the walls of the
building was increased to an R-30.
The R-Value for insulation on the roof was increased
to an R-50. Highly
efficient low-e glazing is being used.
Also, exterior sun shading devices will shade much of
the glazing during the day.
All
of these features contribute to the projected decrease in
energy use by this building of approximately 62 percent.
Commissioning
During
the design phase, a third party commissioning
agent was hired to give input on design decisions and help
make the building as energy efficient as possible.
The commissioning agent reviewed the documents at
different phases to ensure functionality of the building
systems design. The
agent will also make sure the building systems operate at
optimum capacity when complete.
General
Contractor, Construction Manager Selection and Value
Engineering
Because
this project will incorporate many sustainable design ideas,
the project team welcomed additional reviews of the design
documents. The
general contractor and construction manager helped with the
reviews, and also selected quality MEP sub-contractors for
the project. This
is important as the facility will utilize the latest in
technology and energy-efficient equipment.
The
value engineering process provided several opportunities to
re-evaluate building materials and systems, including:
-
Changing
the elevator to a non-hydraulic machine that does not
use hydraulic fluids and uses approximately 50 percent
less energy than the previously selected standard
hydraulic elevator.
-
As
a cost savings measure, the limestone originally
specified for the exterior façade was replaced with a
locally-manufactured brick.
-
After
visiting other under-floor air installations, the team
made a few adjustments to the system so it could provide
more flexibility to the owner.
-
The
support system for the photo-voltaic panels was revised
so it sits on top of the roof, not penetrating the roof
membrane at each support, to help provide a better
overall roof installation.
-
Some
of the specified light fixtures were changed out,
offering savings to the owner while still providing
optimum energy efficiency.
LEED
Pre-Construction Conference
Before
construction started, we held a LEED pre-construction
conference to address questions from the owner, the entire
design and construction team and subcontractors, and the
commissioning agent. At
this meeting, we reviewed the LEED credits the project was
targeting so the entire team had an understanding of the
goals for the project. We
also discussed the process for LEED submittals, what
information would be required, the IAQ plan, the
Construction Waste Management Plan requirements, the
Recycled and Regional materials documentation requirements,
VOC Content, and how to manage all of this information in
support of the final LEED submittal.
LEED
Core & Shell
When
this project was started in 2002, the LEED program available
for the project was
LEED
NC
, which is what the project was registered under.
The LEED Core & Shell Pilot Program has since
become available so we changed the registration of the
project to this program.
While still in the pilot phase, this new program is
designed specifically for speculative office buildings, like
the
McKinney
Green
Building
, and it enables the owner to receive a pre-certification
for the building, which allows them to market it as a LEED
project. This is viewed positively by many prospective
tenants. The
McKinney
Green
Building
recently received a platinum level pre-certification for
design.
Wrap-up
The
project has been under construction for almost six months,
and is scheduled to be complete in April 2006.
Upcoming project milestones on this sustainable
building include:
-
Structural
steel is scheduled to be complete the end of September.
-
The
geo-thermal wells being drilled on the site will be
complete by mid-September.
-
The
storm water retention system installation will begin in
September.
-
MEP
equipment will begin arriving at the site in
mid-September.